[2026] NSWCA 99
This is where clients (especially principals / developers) are most likely to fall into a trap, and can even be ruined financially.
Where are clients most likely to go wrong? (The fatal misconception) Clients often approach legal processes with a simple commercial mindset. When they receive a large invoice from a builder and find that the work has serious defects, or that the builder has not even finished the job, their first reaction is often: “This person is talking nonsense. I’ll ignore him; I’m not paying anyway.” That is exactly what the principal thought in this case. It even believed it could defend the claim in court by arguing that “the builder has not proved that it did the work”. This is a huge trap! Under the SOP Act, “staying silent” does not mean “refusing”; it means **”I accept the whole amount as a matter of law”**.
How to avoid the trap (the lawyer’s emergency measures)
- Set up an alert mechanism: Tell your principal-side clients that any invoice stating “Made under the Building and Construction Industry Security of Payment Act 1999” must be sent to their lawyer for assessment immediately.
- Even if you dispute it, serve a Payment Schedule: If you do not agree to pay, you must, must, must serve a written Payment Schedule within the time limit (usually within 10 business days, or the time specified in the contract). Even if your reason is “the project is a complete mess and I won’t pay a cent ($0)”, you must set out those reasons in the Schedule and send it to the other side. Once you have responded, the blocking mechanism takes effect: the other side cannot go straight to summary judgment, and must instead go through the adjudicator’s review process.
How should clients assess the risk? Before awarding a construction contract, or at the early stage of a dispute, help clients make the following risk assessments:
- Timeline review: Carefully review the “invoicing date” in the contract (such as the 21st of each month in this case) and the “deadline for serving a payment schedule”. Deadlines are fatal under the SOP Act.
- Licensing and insurance review: As in this case, assess whether the work is actually “Residential Building Work”. If it is, immediately check whether the builder has taken out insurance as required by s 92 of the Home Building Act. If it has not, the builder may lose its right to make a claim under the SOP Act altogether (this is a very good defensive weapon, although the defendant in this case used it in the wrong place).
- Understand that “the payment is only interim”: Tell clients that the SOP Act exists only to deal with cash flow. Even if they are compelled to pay now under the SOP Act, that does not mean they have given up their right to pursue the builder for breach of contract. At worst, it is “pay now, then sue for breach later” (Pay now, fight later).
Part 1: Core Concepts Explained
To understand this case, you must first grasp two extremely important legal concepts:
1. The SOP Act (Building and Construction Industry Security of Payment Act) and “Pay now, fight later” In the construction industry, cash flow is everything. To prevent developers (principals) from deliberately withholding progress payments and starving builders (contractors) out of business, New South Wales enacted the SOP Act. The Act establishes a fast interim payment mechanism that does not require cumbersome legal proceedings. Its core philosophy is **”pay now, fight later”**. In other words, the mechanism only decides who should get the money now; whether the work is defective or there has been a breach of contract can be fought out later by the parties in formal litigation or arbitration, but the money must be paid now.
2. The key weapons: the Payment Claim and the Payment Schedule
- Payment Claim: an invoice issued by the builder under the SOP Act, stating that it “claims” to be entitled to the progress payment.
- Payment Schedule: if the developer (principal) does not agree with the amount claimed, it must serve a Payment Schedule within the statutory time limit, stating how much it is prepared to pay and its reasons for withholding the balance.
- The fatal rule: if the principal receives a Payment Claim but does not serve a Payment Schedule, the legal consequences are extremely severe: the principal automatically becomes liable at law to pay the full amount claimed, and the builder can go straight to court to recover the amount as a debt due.
Part 2: The Facts, Step by Step
Now let us apply the concepts to this case.
Background: The plaintiff (the respondent in this appeal), Black Sheep, is a builder, and the defendant (the appellant), Portelli, is a medical trust company (the principal / developer). The parties entered into a contract to build four specialist accommodation buildings providing high physical support for people with disability.
What happened? In August and September 2025, the builder issued payment claims No. 3 and No. 4 (PC3 and PC4), claiming a total of more than three million Australian dollars. The principal, Portelli, then made the cardinal mistake in construction disputes: it neither paid in full nor served a Payment Schedule.
When the builder went to court to recover the money, the principal, Portelli, raised three very stubborn defences (which were also the core issues in this appeal):
- “He hasn’t proved he did the work!”: The principal argued that, to be paid, the builder had to prove objectively that it had actually carried out the work.
- The court said: wrong! The key under the SOP Act is that the builder “claims to be entitled” to be paid. If the court required the builder to prove first that the work had actually been done before it could be paid, that would completely defeat the legislative purpose of the SOP Act, which is to get money flowing quickly. If you thought he hadn’t done the work, why didn’t you serve a Payment Schedule at the time?
- “He served the invoice at the wrong time (too early)!”: The principal argued that the SOP Act only allows a claim to be made at the end of the month, and since the builder served it on the 21st, it was invalid.
- The court said: wrong! Although the default position under the SOP Act is that claims are made at the end of the month, if the parties’ special conditions of contract provide for an earlier date, the claim can be served earlier. In this case, because the principal had engaged a Quantity Surveyor, a special condition of the contract was triggered that allowed, and required, claims to be made on the 21st day of each month, so the time of service of the invoices was entirely valid.
- “This is residential building work and he didn’t take out compulsory insurance!”: Under the Home Building Act, for “residential building work” the builder must take out specific insurance, failing which it is not entitled to claim payment under the SOP Act. The principal argued that the bedrooms it was building for people with disability were “self-contained units” and therefore residential.
- The court said: utterly wrong! In this kind of specialist disability accommodation, residents share the kitchen, living room and laundry, so how could the rooms possibly be “self-contained units”? Merely having a bedroom with an ensuite does not have the features of a “dwelling unit” in the ordinary sense. It was therefore a special facility exempted by law, and did not require that kind of residential insurance
Part 3: What Did the Plaintiff Seek, and Did the Court Agree?
The plaintiff’s (the builder, Black Sheep’s) claim was very straightforward: because the principal had not served a Payment Schedule, under ss 14 and 15 of the SOP Act the amount had become a statutory debt (debt due). The plaintiff applied to the Supreme Court for Summary Judgment, seeking immediate payment. Summary judgment means the plaintiff considers that the case is beyond genuine dispute, so there is no need for a trial of the facts and the judge can decide it directly.
Did the court agree? Entirely. The primary judge entered summary judgment in the builder’s favour for $3,822,378.26 plus interest. The Court of Appeal fully upheld the decision below, dismissed the principal’s appeal, and ordered the principal not only to pay the costs but also to pay the more than A$3.8 million it had previously paid into court to the builder in full, forthwith
Part 4: A Framework for Applying This Type of Claim
As a lawyer, you can characterise this type of case as a **”standard model for recovering debts under the SOP Act”**. In future, whether you act for a builder seeking payment or for a developer defending a claim, you can apply this chain of reasoning directly:
- Jurisdictional precondition: Is there a construction contract between the parties within the meaning of the SOP Act?
- Validity of the document: Is the builder’s Payment Claim valid? (Does it state that it is made under the SOP Act? Does it clearly identify the work and the amount claimed?)
- Time of service: Was it served on the correct date permitted by the legislation or the contract (Reference Date / Named Month)?
- The golden blocking point (crucial!): Did the principal serve a valid Payment Schedule within the statutory time limit?
As long as the first three points are satisfied and the answer to point 4 is “no”, as the builder’s lawyer you can go straight to court and apply for Summary Judgment, without having to argue with the other side about the quality of the work at this stage.