International Arbitration Practice Guide: Precisely Defining the “Matter” and Guarding Against Waiver of the Right to Arbitrate — The Clough Case

中文English
Trap 1: Believing that “once you go to court, arbitration is gone entirely” (The “All or Nothing” Fallacy)
  • The common client mistake: Clients often think that as soon as they file a statement of claim in court, they have completely lost the right to rely on the arbitration clause.
  • How to avoid it: Tell the client that the court looks at the specific “Matter”. Suing on a non-arbitrable matter (such as the effect of an insolvency restructuring) does not cause you to lose the right to arbitrate a purely commercial money dispute. But be careful: you cannot, in respect of the same arbitrable matter, both sue in court and seek to arbitrate.
Trap 2: When sued, “filing a defence first and objecting to jurisdiction later”
  • The common client mistake: A client unexpectedly receives court process and, in a hurry, immediately instructs their lawyer to file a full Defence on the merits.
  • How to avoid it: This is an extremely fatal mistake! Once you defend on the merits, the court will find that you have “intentionally and clearly given up” the right to arbitrate (Waiver). The correct approach, as Elecnor did in this case, is to move for a Stay of the proceedings at the first opportunity (shortly after) once the other side asserts its claim.
Trap 3: Overlooking the third-party risk of claims “Through or Under” a party
  • The common client mistake: Clients assume that because the insolvency Trustees did not sign the original joint venture contract, the arbitration clause cannot bind them.
  • How to avoid it: An arbitration clause can bind “non-signatories”. As long as the right asserted by the third party (such as an insolvency trustee) is “derived” from a contracting party (for example, the trustees in this case seeking contribution towards the bank guarantee call), they are claiming “through or under” that party and must be bound by the arbitration clause.
How should clients assess the risk? When you take on a matter, guide the client through these three risk tests:
  1. Break down the matters: How many baskets does our dispute fall into? Which are pure breach of contract claims? Which involve statutory rights or insolvency?
  2. Test “arbitrability”: Will these matters affect unrelated third parties (such as the body of creditors)? Is any public interest involved? If so, they will most likely have to be fought in court.
  3. Assess the cost of fighting on two fronts: Warn the client that, because the International Arbitration Act is mandatory, the case may very well be “split” into two battlefields, court and arbitration. The client needs to be prepared, in budget and in effort, to fight on two fronts.
Clough Projects Australia Pty Ltd v Elecnor Australia Pty Ltd [2026] NSWCA 111 https://www.caselaw.nsw.gov.au/decision/19eba5177a5676f8379cbe5e This case makes clear that, in an international commercial dispute where one party has entered an insolvency restructuring (DOCA), the court may procedurally split the non-arbitrable statutory dispute (kept in court) from the purely commercial breach of contract cross-claim (sent to arbitration), and that a plaintiff suing on a non-arbitrable matter does not thereby waive or repudiate its right to arbitrate the arbitrable matters
Part 1: Key Concepts
When reading cases involving a conflict between arbitration and litigation, you must first have these four core concepts in mind:
  1. Stay of Proceedings and referral to arbitration: Under s 7(2) of Australia’s International Arbitration Act 1974 (IAA), if the parties have signed an arbitration agreement but one party goes to court, the other party can ask the court to “stay” (pause) the proceedings and send the case back to the arbitral tribunal. This is a mandatory provision: provided the conditions are met, the court must let go of the matter.
  2. The difference between “Proceedings” and a “Matter”: This is the most important distinction in this case. One set of “proceedings” (like a big basket) may contain several different “matters” (the apples in the basket). The court does not have to send the whole proceedings off to arbitration as a package; it can “break up” the proceedings, sending the “matters” that fall within the arbitration to arbitration and keeping the others in court.
  3. Arbitrability: Not every dispute can be resolved by arbitration. Purely private commercial disputes (such as who owes whom money) can be arbitrated. But if a dispute involves the public interest, or a structure established by statute (such as corporate insolvency or liquidation, affecting the interests of third-party creditors), it is a “non-arbitrable” matter and must be determined by the court according to law.
  4. Waiver and Repudiation: If you are entitled to require arbitration but you choose to sue in court, or after being sued you defend on the merits (instead of immediately seeking a stay), you will be treated as having “waived” the right or “repudiated” the agreement, and will lose the right to arbitrate entirely.
Part 2: The Plaintiff’s Claim and the Court’s Decision (Step by Step)
Background: Elecnor (the plaintiff / respondent on appeal) and Clough (the defendant / appellant) formed a Joint Venture and took on a large engineering project. Clough later became insolvent and entered into a “deed of company arrangement” (DOCA, a statutory insolvency restructuring procedure).
The plaintiff’s (Elecnor’s) claim: Elecnor wished to exercise the “default buy-out right” in the contract (Clause 21.3) to acquire Clough’s 50% interest in the joint venture for AUD 1. Elecnor therefore sued, seeking a declaration that the DOCA (insolvency restructuring) had not taken away its buy-out right, and an order for Specific Performance. We will call this the “Clause 21.3 Matter”.
The defendant’s (Clough’s) counter-attack (cross-claim): Clough suddenly cross-claimed: “Wait — the principal previously called on AUD 110 million of bank guarantees that belonged to me, and under the contract you should bear half of that (AUD 55 million)!”. We will call this the “Call Contribution Matter”.
The plaintiff’s clever move and the Court’s decision: Seeing this, Elecnor immediately applied to the Court: keep the “Clause 21.3 Matter” I sued on in court, but stay Clough’s cross-claim, the “Call Contribution Matter”, and send it to arbitration in Singapore!
Did the Court agree? Yes! The Court’s reasoning was very clear:
  1. These are two separate “matters”: The Court held that the dispute over the AUD 1 compulsory buy-out of the interest and the dispute over contribution to the AUD 55 million guarantee call are two separate issues capable of being resolved separately.
  2. Distinguishing arbitrability: The plaintiff’s “Clause 21.3 Matter” involves the DOCA insolvency regime under the Corporations Act, affects the interests of other creditors and has a public character, so it is not arbitrable and must stay in court. The defendant’s cross-claim, the “Call Contribution Matter”, is merely a private contractual money dispute and is arbitrable.
  3. The plaintiff did not waive: The defendant argued that because the plaintiff itself had come to court, it had “given up” arbitration. But the Court held that suing on a “non-arbitrable” matter does not mean the plaintiff waived its right to arbitrate “arbitrable” matters. Moreover, the plaintiff applied for arbitration at the first opportunity after receiving the cross-claim, and there was no indication whatsoever of an intention to waive.
Ultimately, the Court of Appeal upheld the primary decision and dismissed Clough’s appeal, approving the “splitting” of the dispute, with part fought in court and part in arbitration
Part 3: Summary of the Claims and Future Application (Drawing Wider Lessons)
As a lawyer, you can sum this strategy up as: the “fracturing and precision-targeting strategy” (Fracturing of Proceedings).
When to use it: When you act for a client (as plaintiff) and the contract contains an arbitration clause, but you want to use the court’s coercive power to resolve urgent issues involving insolvency, the validity of intellectual property or statutory rights (which are non-arbitrable), you can confidently sue in court. If the other side seizes the chance to bring an ordinary breach of contract cross-claim against you in court, you can immediately invoke s 7(2) of the International Arbitration Act and ask for the cross-claim to be removed from the court and sent to arbitration. This strategy can greatly increase the other side’s litigation costs (they must fight on two fronts at once, in court and before the tribunal), and gives you the procedural initiative.